Procurement of Lift refurbishment Programme and External Repairs and Decorations Programme

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

The decision taken approved the letting of two new contracts for works to its housing stock.

 

The works include:

 

  • the full refurbishment of passenger lifts in seven council owned residential blocks, and
  • a five year term contract for the completion of external cyclical decorations as required.

 

The values of both contracts are detailed in the report and exceed £250,000

Decision:

Cabinet authorised the following:

 

1.  The letting of the contract for the refurbishment of seven passenger lifts, as detailed in the Cabinet report;

 

2.  The letting of a term contract for the completion of a programme of external cyclical decorations, as detailed in the Cabinet report.

Reasons for the decision:

The works identified are essential repairs and maintenance to the council’s housing stock, relating to its duties and responsibilities as a landlord.

Alternative options considered:

The works are considered to be essential and there are no realistic alternatives.

Report author: Bob Porter

Publication date: 10/08/2020

Date of decision: 30/07/2020

Decided at meeting: 30/07/2020 - Cabinet

Effective from: 18/08/2020