Replacement of Berth 4/5 (Port of Ramsgate) and Provision of Commercial Berth (Ramsgate Harbour)

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

There is an urgent need to replace the existing Berth 4/5 (aggregate berth) at the Port of Ramsgate which has reached the end of its operational life.

 

Berth 4/5 is a floating berth which is used for the discharge of aggregates from vessels to the quayside.  The berth is referenced in a legal agreement with Brett Aggregates and the council has a long term obligation to provide a serviceable berth facility.

 

The report included 4 options for delivery including a proposal to provide a Commercial Berth in Ramsgate Harbour.  The options listed in this report described two berth design solutions for the project and two separate procurement routes.

Decision:

Option 4 of the report was approved which included approval of the expenditure of the allocated budget for a floating berth to replace Berth 4/5 only and the seeking of tenders via an open (competitive) route.

Reasons for the decision:

To replace the existing berth which has reached the end of its operational life.  This is necessary to fulfill contractual obligations and enable the continuation of aggregate imports at the Port of Ramsgate.

Alternative options considered:

Options 1,2 and 3 were considered.  These included a direct award route for a floating replacement for Berth 4/5 and a commercial berth in the Royal Harbour. Also included was a piled quay replacement for berth 4/5.  These options were rejected in favour of Option 4.

Publication date: 19/12/2019

Date of decision: 16/12/2019

Decided at meeting: 16/12/2019 - Cabinet

Effective from: 04/01/2020