311 Decarbonisation of the Kent Innovation Centre PDF 103 KB
Additional documents:
Minutes:
Chris Blundell, Finance introduced the report
and gave a PowerPoint slides presentation. He made the following
points:
- These proposals were in line with
the objectives of the scheme;
- The Kent innovation Centre building
had very high usage and reducing its carbon footprint would assist
with the council’s overall objectives of a reduction in the
council’s footprint to carbon neutral by 2030;
- A bid made by the council was
successful and £1.1million had been paid by the end of
March;
- A Cabinet Member decision had been
,made to add the project to the council’s Capital Programme
for 2021/22;
- There was a September 2021 to get
the project underway;
- The building would be insulated to
make it energy efficient;
- The aging gas heaters would be
replaced with air source heat pumps;
- Renewable electricity will be
installed;
- The project was being financed from
external sources;
- There were some risks that would
need to be managed;
- TDC would like the way in order to
motivate the community.
Members asked questions and made comments as
follows:
- This was a good project. Will the
LED lights to be installed controllable and consideration be given
to people with disabilities?
- Was this planned to be a major
construction that would later be used by organisations that could
include TDC?
- It was said that air source heat
pumps only work if the if the walls were insulated;
- There was Member support for this
work;
- This was a good example of
incorporating ecological concerns on major construction works and
this would be beneficial to the council;
- The project cost would be
£1.236million against a grant of £1.1million. Could
officers assure Members that the project costs would stay within
the fund limit?
- If there were anticipated costs
overruns, why not get a fixed cost tender?
- Would any cost overruns be reported
to the Panel?
Mr Blundell and Ms Homer responded as
follows:
- This was the first of many more
projects to come. The council had committed £3million for
council offices and green criteria would be considered when
sourcing for these offices;
- Currently there are tenants in the
KIC building. The council was in the process of reviewing its
council base (offices) and reviewing its future options for
efficient working;
- KIC had an 85% occupancy of the
building;
- There was some substantial work
being done to the wall insulation and these works were being
carried out around the organisations currently suing the office
space;
- There were risks for cost overruns
of the projects. There was therefore a need to keep an eye on that.
The project had a 10% contingency built in;
- Although there was a main
contractor, there were several suppliers involved in the project.
It was therefore not possible to get a single fixed cost tender due
to the nature of the project;
- Officers would be reporting to the
Panel on any overruns.
After the discussion, Members noted the
proposals.