Issue - meetings

Cabinet approve expenditure of £1.1m to be incurred at the KIC for the decarbonisation of the site

Meeting: 25/05/2021 - Overview & Scrutiny Panel (Item 311)

311 Decarbonisation of the Kent Innovation Centre pdf icon PDF 103 KB

Additional documents:

Minutes:

Chris Blundell, Finance introduced the report and gave a PowerPoint slides presentation. He made the following points:

 

  • These proposals were in line with the objectives of the scheme;
  • The Kent innovation Centre building had very high usage and reducing its carbon footprint would assist with the council’s overall objectives of a reduction in the council’s footprint to carbon neutral by 2030;
  • A bid made by the council was successful and £1.1million had been paid by the end of March;
  • A Cabinet Member decision had been ,made to add the project to the council’s Capital Programme for 2021/22;
  • There was a September 2021 to get the project underway;
  • The building would be insulated to make it energy efficient;
  • The aging gas heaters would be replaced with air source heat pumps;
  • Renewable electricity will be installed;
  • The project was being financed from external sources;
  • There were some risks that would need to be managed;
  • TDC would like the way in order to motivate the community.

 

Members asked questions and made comments as follows:

 

  • This was a good project. Will the LED lights to be installed controllable and consideration be given to people with disabilities?
  • Was this planned to be a major construction that would later be used by organisations that could include TDC?
  • It was said that air source heat pumps only work if the if the walls were insulated;
  • There was Member support for this work;
  • This was a good example of incorporating ecological concerns on major construction works and this would be beneficial to the council;
  • The project cost would be £1.236million against a grant of £1.1million. Could officers assure Members that the project costs would stay within the fund limit?
  • If there were anticipated costs overruns, why not get a fixed cost tender?
  • Would any cost overruns be reported to the Panel?

 

Mr Blundell and Ms Homer responded as follows:

 

  • This was the first of many more projects to come. The council had committed £3million for council offices and green criteria would be considered when sourcing for these offices;
  • Currently there are tenants in the KIC building. The council was in the process of reviewing its council base (offices) and reviewing its future options for efficient working;
  • KIC had an 85% occupancy of the building;
  • There was some substantial work being done to the wall insulation and these works were being carried out around the organisations currently suing the office space;
  • There were risks for cost overruns of the projects. There was therefore a need to keep an eye on that. The project had a 10% contingency built in;
  • Although there was a main contractor, there were several suppliers involved in the project. It was therefore not possible to get a single fixed cost tender due to the nature of the project;
  • Officers would be reporting to the Panel on any overruns.

 

After the discussion, Members noted the proposals.