Berth 4/5 - Port of Ramsgate - Additional Funding

The delivery of the berth 4/5 project has been delayed whilst an Environmental Impact Assessment (EIA) is undertaken to inform the planning and marine licence consents process. This unanticipated delay has resulted in a significant increase in the estimated total cost of the scheme which now exceeds the allocated budget.

Decision type: Key

Reason Key: Expenditure or Making one-off Savings anticipated to be £250,000 or more*;

Decision status: Recommendations Approved

Wards affected: Central Harbour Ward;

Notice of proposed decision first published: 23/06/2021

Decision due: 29 Jul 2021 by Cabinet

Lead member: Councillor Ash Ashbee, Leader of the Council cllr-ash.ashbee@thanet.gov.uk

Lead director: Gavin Waite

Contact: Mike Humber, Director of Environment Tel: 01843 577083 Email: mike.humber@thanet.gov.uk.

What the decision will mean: Increase in capital and revenue budget value for the Berth 4/5 project