Issue - meetings

Question No.1 Broadstairs Playgrounds

Meeting: 10/10/2019 - Council (Item 7)

7 Question No.1 Broadstairs Playgrounds pdf icon PDF 180 KB

Minutes:

Councillor Garner asked Councillor Ashbee the following question:

 

“Plans to replace the 4 playgrounds in Broadstairs parks, along with the Section 106 funding to pay for them, have been waiting for approval since last year. Can you confirm when the 4 new playgrounds will be installed?”

 

Councillor Ashbee responded with the following points:

 

A programme had been drafted for the playground refurbishment works.  Completion of the site works was programmed for the end of June 2020.

 

Councillor Garner  followed up his question by asking if residents could be engaged at an early stage in the process, and involved in the planning of the playgrounds.

 

Councillor Ashbee responded that she would be very happy to coordinate a meeting with the residents and planners in order to have input from residents.