Venue: Council Chamber, Council Offices, Cecil Street, Margate, Kent. View directions
Contact: Charles Hungwe
No. | Item |
---|---|
Apologies for Absence Minutes: Apologies were received from Councillor Connor. |
|
Declarations of Interest To receive any declarations of interest. Members are advised to consider the advice contained within the Declaration of Interest form attached at the back of this agenda. If a Member declares an interest, they should complete that form and hand it to the officer clerking the meeting and then take the prescribed course of action. Minutes: There were no declarations of interest. |
|
Minutes of Previous Meeting PDF 30 KB To approve the Minutes of the Corporate Performance Review Working Party meeting held on 13 November 2017, copy attached. Minutes: Councillor Rusiecki proposed, Councillor Campbell seconded and Members agreed the minutes as a correct record of the meeting that was held on 13 November 2017. |
|
TDC Corporate Performance Report Quarter 3 2017/18 PDF 95 KB Additional documents:
Minutes: Hannah Thorpe, Head of Communications introduced the item and made the following comments:
After the presentation, Members made comments and asked questions as follows:
In response to Member comments and questions, Hannah Thorpe, Trevor Kennett (Head of Operational Services) and Tim Willis (Director of Corporate Resources) made the following comments:
|
|
EK Services Q3 2017/18 Performance Report for TDC PDF 64 KB Additional documents: Minutes: Dominic Whelan, Director of Shared Services introduced the item for discussion and highlighted the following:
· Overall performance by ICT and HR is good. Most income collections performance was also good; · Business Rates: Business Rates collection for December was slightly below the expected levels. However, this will improve in the next quarter as there were significant payments from two large contributors that were due in December but were actually received in early January 2018; · Customer Services: The service level remains below target. Mr Whelan explained that the reasons for this have been explained in depth over the past few quarters and are due to ongoing resource pressures within Customer Services. However, the measures outlined by Mr Whelan at the previous quarter report, including re-deployment of staff and apprenticeship programme have had a positive impact on the performance of the call centre with average call waiting time improving from 1minute 53 seconds last quarter to 1minute 34seconds; · Risks: There was a high level of risk that the performance targets for Customer Services Call Waiting would not be met and EKS had discussions with Tim Willis and Madeline Homer to explore the possibility of re-assessing the targets; · Key Initiatives: It was worth noting that digital benefits processing system was now operational and there was marked uptake of the new service by customers. The system was intuitive, makes it much easier to upload evidence and is linked to the Risk Based Verification process that means the amount and type of evidence documentation required to be presented by citizens is flexible depending on individual risk scores.
Members noted the report.
|
|
East Kent Housing Performance Report Q3 2017/18 PDF 102 KB Minutes: Deborah Upton, CEx of East Kent Housing introduced the item and highlighted the following:
· Universal Credit and Income: Performance started to recover in January 2018; · In Thanet there were 350 cases of individuals on Universal Credit. There were challenges in processing claims for individuals on Universal Credit as they had to go without payments for the first 45 days of being moved to the Universal Credit system; · This delay could extend by another six weeks and this may affect tenants ability to pay rent. However EKH has not evicted any tenants affected by the delays caused by switching to Universal Credit; · To cut down on delays EKH assigned additional staff to support the processing of Universal Credit claims as it takes longer to process such applications than processing housing benefits claims; · Some study has indicated that it takes about six months for an individual who has moved to Universal Credit to get back from arrears and be up to date with their rent payments; · There are similar experiences in neighbouring councils; · Garage arrears have gone down 40% where resources have been increased to support that revenue collection service; · The performance regarding management of voids is strong;
Contributing to the same discussion, Mark Anderson, Director of Property Services (EKH) added the following comments:
· Capital Programme: There was a 23.69% underspend in the capital programme budget. The original approved council budget was £4.2 million and just over £1 million had so been spent by 31 December 2017. If commitments were added to these figures, then the spend would be £1.6million; · By financial year end the spend would be circa £2.5-£2.6million. This was because there were still a number of large projects to be undertaken. · The largest of these projects being Royal Crescent which had an allocation of about £1million on its own; · There was a need to carry out a feasibility study to determine whether it was appropriate to spend a huge sum of money on this one property; · As a result this would have to be deferred to 2018/19 financial year; · Over the past three years, there had been a decrease in percentage of residents responding to the tenants’ survey; · As a result EKH were developing a more effective survey to test tenants’ views on the service provided by EKH and services providers contracted by EKH; · The new survey structure has been piloted in the last three months. This will be reviewed in the coming quarter to determine its effectiveness; · Gas Servicing: Less than 20% of tenants who receive a service from P&R respond to their survey. EKH had been receiving an increasing number of complaints about the P&R service. EKH were looking into that issue.
Responding to the officer presentations Members made comments and asked questions as follows:
· Can tenants on Universal Credit get direct payments to the landlord? · Was there a budget for disabled facilities adaptations? · What was the performance of the disabled facilities modifications? · Was the performance on track or not?
Ms Upton and Mr Anderson ... view the full minutes text for item 230. |