Issue details

Port and Harbour Projects - Variation to 2019/20 Capital Programme

This report proposes that a project to deliver the Commercial Berth - (Eastern Gully, Ramsgate Harbour) be approved for inclusion in the 2019/20 capital programme, and for the project to be funded via the reallocation of part of an existing 2019-20 capital project budget. The existing 2019-20 project from which funds are proposed to be realigned is the Port of Ramsgate Berth 4/5 project.

Decision type: Non-key

Decision status: Recommendations Approved

Notice of proposed decision first published: 20/09/2019

Decision due: 20 Sep 2019 by Leader of the Council and Cabinet Member for Strategy and Transformation

Lead member: Councillor Robert W Bayford, Cabinet Member for Environmental Services & Special Projects cllr-robert.bayford@thanet.gov.uk

Lead director: Gavin Waite

Contact: Mike Humber, Director of Environment Tel: 01843 577083 Email: mike.humber@thanet.gov.uk.

Decisions